CONSTRUCTION
UPDATES
See what’s going on behind the scenes of CORE.
Cosumnes CSD is constructing a new recreation and fitness facility that will span across two stories and 59,000 square feet. The top-notch facility will be situated on 4 acres of undeveloped land within Morse Community Park, at the intersection of Bellaterra Drive and Fire Poppy Drive. CORE Recreation Center will offer a diverse range of programs and amenities for the community to come together, have fun, and maintain a healthy lifestyle.
Check back often for construction updates.
MILESTONES
-
Early 2025
Grand Opening
-
2023-2024
Construction will last approximately 20 months.
-
2023
Cosumnes CSD Board awards construction contract to S J Amoroso through a public bid process.
-
2022
Final recreation center design totals 59,000 square feet with two gyms, three group exercise studios, a fitness deck, an indoor track, outdoor functional fitness, an outside bouldering area, additional parking, and new landscaping.
-
2021
Cosumnes CSD Board approves Barker, Rinker, and Seacat Architecture (BRS) of Denver, CO, to design the recreation center. BRS conducts public meetings to review the building and confirm the design.
-
2020
Cosumnes CSD Board approves a Business and Operations Plan based on the feasibility study.
-
2019
A feasibility study by GreenPlay, LLC confirms community support and financial viability of a new recreation center. Over 1,100 residents provide input and ideas through public meetings and surveys.
-
2017
Cosumnes Parks & Recreation Master Plan proposes the development of a recreation center in Morse Community Park.
-
2008
Morse Community Park opens. Four acres are reserved for a future recreation center.
-
2003
Recreation center identified for community park in East Franklin Specific Plan.